Back to projects

Connect Antoine-Labelle - construction of the FTTH network

Chute-Saint-Philippe, Quebec

completeBroadband And ConnectivityRNIS
Federal contribution
$12.0M
$12,045,490
Federal share37%

of $32.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 25, 2019
201920202021202220232024
Built
Program
Rural & Northern Infrastructure Stream
Construction start
Sep 30, 2019(actual)
Construction end
Aug 31, 2024(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Aug 5, 2019
  • Construction end4 weeks earlyforecast Sep 30, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53577 in the federal list. How to read these figures.