Powerplant Infrastructure Upgrades in Pond Inlet, Clyde River and Whale Cove
Federal contribution
$4.4M
$4,425,000
Federal share52%
of $8.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2019
202020212022
Built
Approved 4 weeks before the announcement.
- Program
- Arctic Energy Fund
- Ultimate recipient
- Qulliq Energy Corporation (QEC)
- Construction start
- Sep 18, 2021(actual)
- Construction end
- Apr 30, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 5, 2021
- Construction end4 weeks lateforecast Mar 31, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53600 in the federal list. How to read these figures.