Back to projects

Powerplant Infrastructure Upgrades in Pond Inlet, Clyde River and Whale Cove

Clyde River, Nunavut

completeGreen EnergyAEF
Federal contribution
$4.4M
$4,425,000
Federal share52%

of $8.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 21, 2019
202020212022
Built

Approved 4 weeks before the announcement.

Program
Arctic Energy Fund
Construction start
Sep 18, 2021(actual)
Construction end
Apr 30, 2022(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 5, 2021
  • Construction end4 weeks lateforecast Mar 31, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53600 in the federal list. How to read these figures.