Implementation of Priority Measures for Public Transit on Boulevard Guillaume-Couture in Lévis
Federal contribution
$25.6M
$25,553,345
Federal share34%
of $75.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 7, 2019
today
2020202220242026
BuiltForecast
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Société de transport de Lévis (STL)
- Construction start
- Jun 20, 2023(actual)
- Construction end
- Jun 29, 2027(forecast)
Also in Lévis