Upgrades to a Sewage Lagoon in Kugaaruk
Federal contribution
$3.6M
$3,637,754
Federal share100%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2019
2020
Built
Approved 2 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Government of Nunavut
- Construction start
- Jun 22, 2019(actual)
- Construction end
- Oct 15, 2020(actual)
Against the original forecast
- Construction end2 weeks earlyforecast Oct 31, 2020
Also in Kugaaruk
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53669 in the federal list. How to read these figures.