Carcross Lagoon Upgrades
Federal contribution
$3.0M
$3,000,000
Federal share68%
of $4.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 24, 2020
202020212022
Built
Approved 17 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Government of Yukon
- Construction start
- May 1, 2020(actual)
- Construction end
- Oct 5, 2022(actual)
Against the original forecast
- Construction start10 months lateforecast Jul 15, 2019
- Construction end4 weeks earlyforecast Oct 31, 2022
Also in Carcross
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53713 in the federal list. How to read these figures.