Rehabilitation Work: Bundle 2 of Level of Service 2 Corridors

Belle Plaine, Saskatchewan

completeHighways and RoadsNRP
Federal contribution
$12.4M
$12,419,753
Federal share48%

of $26.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2019
202020212022202320242025
Built

Approved 4 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
Province of Saskatchewan
Construction start
Sep 2, 2019(actual)
Construction end
Jul 9, 2025(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2019
  • Construction end5 months earlyforecast Nov 30, 2025

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53737 in the federal list. How to read these figures.