Rural Road Rehabilitation - Avalon Region
Carbonear, Newfoundland and Labrador
Federal contribution
$3.0M
$2,973,597
Federal share50%
of $5.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
20202021
Built
Approved 3 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Government of Newfoundland and Labrador
- Construction start
- Jul 21, 2019(actual)
- Construction end
- Sep 13, 2021(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 1, 2019
- Construction end3 months earlyforecast Nov 30, 2021