Rural Road Rehabilitation - Avalon Region

Carbonear, Newfoundland and Labrador

completeHighways and RoadsRNIS
Federal contribution
$3.0M
$2,973,597
Federal share50%

of $5.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
20202021
Built

Approved 3 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jul 21, 2019(actual)
Construction end
Sep 13, 2021(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 1, 2019
  • Construction end3 months earlyforecast Nov 30, 2021

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53739 in the federal list. How to read these figures.