Rural Road Rehabilitation - Eastern Region
Chapel Arm, Newfoundland and Labrador
Federal contribution
$5.0M
$4,968,000
Federal share50%
of $9.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
20202021202220232024
Built
Approved 8 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Government of Newfoundland and Labrador
- Construction start
- Jun 24, 2019(actual)
- Construction end
- Nov 30, 2023(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 1, 2019
- Construction end13 months lateforecast Oct 31, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53767 in the federal list. How to read these figures.