Harrietsfield Remediation

Halifax, Nova Scotia

completeBrownfield Remediation And RedevelopmentGIS
Federal contribution
$6.8M
$6,781,000
Federal share42%

of $16.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2019
20202021
Built
Program
Green Infrastructure Stream
Ultimate recipient
Province of Nova Scotia
Construction start
May 21, 2020(actual)
Construction end
Oct 29, 2021(actual)

Against the original forecast

  • Construction start4 months lateforecast Jan 15, 2020
  • Construction end3 months lateforecast Aug 2, 2021

Also in Halifax

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53771 in the federal list. How to read these figures.