Harrietsfield Remediation
Federal contribution
$6.8M
$6,781,000
Federal share42%
of $16.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2019
20202021
Built
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Province of Nova Scotia
- Construction start
- May 21, 2020(actual)
- Construction end
- Oct 29, 2021(actual)
Against the original forecast
- Construction start4 months lateforecast Jan 15, 2020
- Construction end3 months lateforecast Aug 2, 2021
Also in Halifax
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53771 in the federal list. How to read these figures.