Town of Vegreville Agri-Food Industrial Park

Vegreville, Alberta

completeWastewaterRNIS
Federal contribution
$5.0M
$4,950,000
Federal share50%

of $9.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 2, 2020
2021202220232024
Built
Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Vegreville
Construction start
Aug 12, 2021(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 1, 2021

Also in Vegreville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53787 in the federal list. How to read these figures.