Back to projects

Boat Launch Recapitalization

Undefined, Yukon

completeMarineRNIS
Federal contribution
$3.1M
$3,101,250
Federal share75%

of $4.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 4, 2019
2020202220242026
Built

Approved 2 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Government of Yukon
Construction start
Oct 6, 2020(actual)
Construction end
Oct 31, 2025(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 1, 2020
  • Construction end12 months earlyforecast Oct 31, 2026

Also in Undefined