Boat Launch Recapitalization
Federal contribution
$3.1M
$3,101,250
Federal share75%
of $4.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2019
2020202220242026
Built
Approved 2 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Government of Yukon
- Construction start
- Oct 6, 2020(actual)
- Construction end
- Oct 31, 2025(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 1, 2020
- Construction end12 months earlyforecast Oct 31, 2026
Also in Undefined
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53788 in the federal list. How to read these figures.