Schedule

Announced and approvedJul 26, 2019
20202021
Built
Program
Green Infrastructure Stream
Ultimate recipient
Town of Isle aux Morts
Construction start
Sep 14, 2020(actual)
Construction end
Dec 17, 2020(actual)