Back to projects

Steady Waterline Extension

River of Ponds, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$98,631
Federal share40%

of $246.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
2020
Built

Approved 5 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Rivers of Ponds
Construction start
Sep 22, 2020(actual)
Construction end
Oct 1, 2020(actual)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53839 in the federal list. How to read these figures.