Road Extension Kelland Drive
Happy Valley-Goose Bay, Newfoundland and Labrador
Federal contribution
$589,030
Federal share32%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
20202021
Built
Approved 3 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Happy Valley-Goose Bay
- Construction start
- May 6, 2021(actual)
- Construction end
- Sep 28, 2021(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Jun 5, 2021
- Construction end4 weeks lateforecast Aug 30, 2021
Also in Happy Valley-Goose Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53853 in the federal list. How to read these figures.