Back to projects

Reservoir and Pump House Improvements - Main Brook

Main Brook, Newfoundland and Labrador

completeDrinking WaterRNIS
Federal contribution
$71,526
Federal share39%

of $181.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
20202021
Built

Approved 3 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Main Brook
Construction start
Aug 3, 2021(actual)
Construction end
Sep 30, 2021(actual)

Against the original forecast

  • Construction start14 months lateforecast May 30, 2020
  • Construction end14 months lateforecast Jul 30, 2020

Also in Main Brook

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53854 in the federal list. How to read these figures.