Back to projects

Town of Baine Harbour - Water Treatment And Chlorination Upgrades

Baine Harbour, Newfoundland and Labrador

completeDrinking WaterRNIS
Federal contribution
$198,106
Federal share40%

of $495.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
202020212022
Built

Approved 3 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Baine Harbour
Construction start
May 31, 2021(actual)
Construction end
Jul 25, 2022(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Apr 30, 2021
  • Construction end8 months earlyforecast Mar 31, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53863 in the federal list. How to read these figures.