Town of Baine Harbour - Water Treatment And Chlorination Upgrades
Baine Harbour, Newfoundland and Labrador
Federal contribution
$198,106
Federal share40%
of $495.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
202020212022
Built
Approved 3 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Baine Harbour
- Construction start
- May 31, 2021(actual)
- Construction end
- Jul 25, 2022(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 30, 2021
- Construction end8 months earlyforecast Mar 31, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53863 in the federal list. How to read these figures.