Water System Upgrades - Mine Hill

Little Bay, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$94,207
Federal share40%

of $235.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
20202021
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Little Bay
Construction start
Jul 21, 2021(actual)
Construction end
Sep 9, 2021(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2021
  • Construction end2 months lateforecast Jul 1, 2021