Schedule
Announced and approvedJul 26, 2019
20202021
Built
Approved 3 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Fox Cove-Mortier
- Construction start
- May 20, 2020(actual)
- Construction end
- Aug 26, 2021(actual)
Against the original forecast
- Construction start3 weeks lateforecast May 1, 2020
- Construction end6 months earlyforecast Feb 28, 2022