Southport Water System Improvements - Phase 1

Caplin Cove-Southport, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$36,636
Federal share40%

of $91.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
20202021
Built
Program
Green Infrastructure Stream
Construction start
Sep 20, 2020(actual)
Construction end
Oct 14, 2021(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2020
  • Construction end10 months lateforecast Dec 15, 2020

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53928 in the federal list. How to read these figures.