Main Street Water Main Replacement - Twilingate
Twillingate, Newfoundland and Labrador
Federal contribution
$1.0M
$1,040,455
Federal share40%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
202020212022
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Twillingate
- Construction start
- Oct 5, 2020(actual)
- Construction end
- Jul 15, 2022(actual)
Against the original forecast
- Construction start5 months lateforecast May 15, 2020
- Construction end7 months lateforecast Dec 5, 2021
Also in Twillingate
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53936 in the federal list. How to read these figures.