Main Street Water Main Replacement - Twilingate

Twillingate, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$1.0M
$1,040,455
Federal share40%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
202020212022
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Twillingate
Construction start
Oct 5, 2020(actual)
Construction end
Jul 15, 2022(actual)

Against the original forecast

  • Construction start5 months lateforecast May 15, 2020
  • Construction end7 months lateforecast Dec 5, 2021