Back to projects

Upgrading of 2 lift stations

Jackson's Arm, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$87,971
Federal share40%

of $219.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
2020
Built

Approved 5 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Jackson's Arm
Construction start
Sep 30, 2020(actual)
Construction end
Nov 26, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 30, 2020

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53937 in the federal list. How to read these figures.