New Submersible Pumps – King's Point

King's Point, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$18,839
Federal share40%

of $47.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
202020212022
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of King's Point
Construction start
Feb 17, 2022(actual)
Construction end
Mar 17, 2022(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jan 15, 2022
  • Construction end2 weeks earlyforecast Mar 31, 2022