New Submersible Pumps King's Point
King's Point, Newfoundland and Labrador
Federal contribution
$18,839
Federal share40%
of $47.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
202020212022
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of King's Point
- Construction start
- Feb 17, 2022(actual)
- Construction end
- Mar 17, 2022(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jan 15, 2022
- Construction end2 weeks earlyforecast Mar 31, 2022
Also in King's Point
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53942 in the federal list. How to read these figures.