Back to projects

Newtown Water and Sewer

Grand Le Pierre, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$91,271
Federal share40%

of $229.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
2020
Built

Approved 5 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Grands of Pierre
Construction start
Jun 15, 2020(actual)
Construction end
Jul 8, 2020(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 15, 2020
  • Construction end8 weeks earlyforecast Sep 1, 2020

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53943 in the federal list. How to read these figures.