Sewage Pumping Stations Retrofit - Nippers Harbour

Nippers Harbour, Newfoundland and Labrador

completeWastewaterRNIS
Federal contribution
$87,937
Federal share39%

of $226.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
20202021
Built

Approved 3 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Nippers Harbour
Construction start
Jul 20, 2020(actual)
Construction end
Dec 14, 2020(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 30, 2020
  • Construction end4 months earlyforecast Mar 31, 2021