Sewage System Repairs - Point Lance
Point Lance, Newfoundland and Labrador
Federal contribution
$91,409
Federal share40%
of $228.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
2020
Built
Approved 3 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Point Lance
- Construction start
- Jul 20, 2020(actual)
- Construction end
- Aug 27, 2020(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2020
- Construction end7 weeks earlyforecast Oct 15, 2020
Also in Point Lance
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53949 in the federal list. How to read these figures.