Watermain Replacement

St. Shott's, Newfoundland and Labrador

completeDrinking WaterRNIS
Federal contribution
$141,129
Federal share40%

of $352.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
20202021
Built

Approved 3 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of St. Shotts
Construction start
May 25, 2020(actual)
Construction end
Sep 21, 2021(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Apr 15, 2020
  • Construction end10 months lateforecast Nov 30, 2020

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53951 in the federal list. How to read these figures.