Storm Sewer Upgrade, Main Street - Cox's Cove
Cox's Cove, Newfoundland and Labrador
Federal contribution
$62,666
Federal share27%
of $232.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
20202021
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Coxs Cove
- Construction start
- Jul 27, 2021(actual)
- Construction end
- Oct 26, 2021(actual)
Against the original forecast
- Construction start2 months lateforecast May 24, 2021
- Construction end6 weeks earlyforecast Dec 7, 2021
Also in Cox's Cove
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53953 in the federal list. How to read these figures.