Back to projects

Water system upgrades on Juniper Stump

Makinsons, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$39,258
Federal share40%

of $98.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
2020
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Makinsons
Construction start
Jul 6, 2020(actual)
Construction end
Oct 3, 2020(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 1, 2020
  • Construction end4 weeks earlyforecast Oct 31, 2020

Also in Makinsons

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53965 in the federal list. How to read these figures.