Water system upgrades on Juniper Stump
Makinsons, Newfoundland and Labrador
Federal contribution
$39,258
Federal share40%
of $98.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
2020
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Makinsons
- Construction start
- Jul 6, 2020(actual)
- Construction end
- Oct 3, 2020(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jun 1, 2020
- Construction end4 weeks earlyforecast Oct 31, 2020