Partial Water, Sewer and Roads Replacement/Improvement - Scott Avenue

Buchans, Newfoundland and Labrador

completeWastewaterRNIS
Federal contribution
$313,946
Federal share40%

of $784.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
202020212022
Built

Approved 3 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Buchans
Construction start
Jun 28, 2021(actual)
Construction end
Jul 15, 2022(actual)

Against the original forecast

  • Construction start8 weeks lateforecast May 1, 2021
  • Construction end2 weeks lateforecast Jun 28, 2022

Also in Buchans