Partial Water, Sewer and Roads Replacement/Improvement - Scott Avenue
Buchans, Newfoundland and Labrador
Federal contribution
$313,946
Federal share40%
of $784.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
202020212022
Built
Approved 3 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Buchans
- Construction start
- Jun 28, 2021(actual)
- Construction end
- Jul 15, 2022(actual)
Against the original forecast
- Construction start8 weeks lateforecast May 1, 2021
- Construction end2 weeks lateforecast Jun 28, 2022
Also in Buchans