Back to projects

Rehabilitation Work: Bundle 2 for Level of Service 1

Delisle, Saskatchewan

completeHighways and RoadsNRP
Federal contribution
$7.8M
$7,830,004
Federal share50%

of $15.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2019
202020212022202320242025
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
Province of Saskatchewan
Construction start
Jun 19, 2020(actual)
Construction end
Dec 31, 2024(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 6, 2020
  • Construction end4 weeks lateforecast Nov 30, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54028 in the federal list. How to read these figures.