Rehabilitation Work: Bundle 2 for Level of Service 1
Federal contribution
$7.8M
$7,830,004
Federal share50%
of $15.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2019
202020212022202320242025
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of Saskatchewan
- Construction start
- Jun 19, 2020(actual)
- Construction end
- Dec 31, 2024(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 6, 2020
- Construction end4 weeks lateforecast Nov 30, 2024
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54028 in the federal list. How to read these figures.