North Okanagan Wastewater Recovery
Spallumcheen, British Columbia
Federal contribution
$13.3M
$13,255,148
Federal share40%
of $33.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 27, 2019
today
20202022202420262028
BuiltForecast
Approved 8 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Township of Spallumcheen
- Construction start
- May 4, 2026(forecast)
- Construction end
- Apr 29, 2028(forecast)
Also in Spallumcheen