Back to projects

Hagensborg Community Potable Water Distribution and Treatment

Central Coast, British Columbia

completeDrinking WaterGIS
Federal contribution
$2.1M
$2,064,800
Federal share40%

of $5.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 27, 2019
2020202220242026
Built

Approved 5 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Nov 15, 2024(actual)
Construction end
Mar 31, 2026(actual)

Against the original forecast

  • Construction start19 months lateforecast Apr 15, 2023
  • Construction end3 months lateforecast Dec 19, 2025

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54070 in the federal list. How to read these figures.