Hagensborg Community Potable Water Distribution and Treatment
Central Coast, British Columbia
Federal contribution
$2.1M
$2,064,800
Federal share40%
of $5.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 27, 2019
2020202220242026
Built
Approved 5 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Central Coast Regional District
- Construction start
- Nov 15, 2024(actual)
- Construction end
- Mar 31, 2026(actual)
Against the original forecast
- Construction start19 months lateforecast Apr 15, 2023
- Construction end3 months lateforecast Dec 19, 2025
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54070 in the federal list. How to read these figures.