Sewer System Upgrade - Fermeuse
Fermeuse, Newfoundland and Labrador
Federal contribution
$284,955
Federal share40%
of $712.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
202020212022202320242025
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Fermeuse
- Construction start
- Jul 27, 2023(actual)
- Construction end
- Dec 21, 2024(actual)
Against the original forecast
- Construction start16 months lateforecast Apr 1, 2022
- Construction end6 months earlyforecast Jun 30, 2025
Also in Fermeuse
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54144 in the federal list. How to read these figures.