Sewer System Upgrade - Fermeuse

Fermeuse, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$284,955
Federal share40%

of $712.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
202020212022202320242025
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Fermeuse
Construction start
Jul 27, 2023(actual)
Construction end
Dec 21, 2024(actual)

Against the original forecast

  • Construction start16 months lateforecast Apr 1, 2022
  • Construction end6 months earlyforecast Jun 30, 2025