Back to projects

Expansion Project for the Biomethanization Facility of the SÉMECS (Société d'économie mixte de l'est de la couronne sud)

Varennes, Quebec

completeGreen EnergyGIS
Federal contribution
$25.2M
$25,200,000
Federal share26%

of $96.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 16, 2022
20202021202220232024
Built

Approved 2.8 years before the announcement.

Program
Green Infrastructure Stream
Construction start
Aug 24, 2020(actual)
Construction end
Sep 30, 2024(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Aug 1, 2020

Also in Varennes