Replacement of Bridge 11

Grand Valley, Ontario

completeHighways and RoadsRNIS
Federal contribution
$365,355
Federal share60%

of $608.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 19, 2019
2020
Built
Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Grand Valley
Construction start
Oct 15, 2019(actual)
Construction end
Mar 26, 2020(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Sep 16, 2019
  • Construction end6 months earlyforecast Sep 15, 2020

Also in Grand Valley

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54223 in the federal list. How to read these figures.