Victoria HandyDART Operations and Maintenance Facility
Federal contribution
$21.8M
$21,842,815
Federal share40%
of $54.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 20, 2019
today
2020202220242026
BuiltForecast
Approved 4 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- British Columbia Transit
- Construction start
- Nov 15, 2021(actual)
- Construction end
- Jan 1, 2027(forecast)
Against the original forecast
- Construction start6 weeks lateforecast Oct 1, 2021