Lutsel K’e – New Diesel Power Plant Facility

Lutsel K’e, Northwest Territories

completeGreen EnergyAEF
Federal contribution
$8.8M
$8,775,000
Federal share75%

of $11.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 30, 2019
2020202120222023
Built

Approved 4 weeks before the announcement.

Program
Arctic Energy Fund
Construction start
Jun 1, 2021(actual)
Construction end
Jan 26, 2023(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Dec 31, 2022