Lutsel Ke New Diesel Power Plant Facility
Lutsel Ke, Northwest Territories
Federal contribution
$8.8M
$8,775,000
Federal share75%
of $11.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 30, 2019
2020202120222023
Built
Approved 4 weeks before the announcement.
- Program
- Arctic Energy Fund
- Ultimate recipient
- Northwest Territories Power Corporation (NTPC)
- Construction start
- Jun 1, 2021(actual)
- Construction end
- Jan 26, 2023(actual)
Against the original forecast
- Construction end4 weeks lateforecast Dec 31, 2022
Also in Lutsel Ke
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54241 in the federal list. How to read these figures.