Taltson Hydroelectric Facility – Major Overhaul

Enterprise, Northwest Territories

completeGreen EnergyGIS
Federal contribution
$17.8M
$17,820,000
Federal share75%

of $23.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 30, 2019
2020202220242026
Built

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Feb 1, 2023(actual)
Construction end
Oct 15, 2025(actual)

Against the original forecast

  • Construction end8 months lateforecast Jan 31, 2025

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54295 in the federal list. How to read these figures.