Prince George to Terrace Capacitors Project: Enabling Electrification of Industry

Burns Lake, British Columbia

underwayGreen EnergyGIS
Federal contribution
$97.0M
$96,950,000
Federal share50%

of $193.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 13, 2025
today
2021202320252027
BuiltForecast

Approved 4.5 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
BC Hydro
Construction start
Jan 10, 2023(actual)
Construction end
Jul 15, 2027(forecast)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54297 in the federal list. How to read these figures.