Eskasoni First Nation Residential Fiber Optic
Federal contribution
$2.5M
$2,505,825
Federal share75%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2019
202020212022
Built
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Eskasoni First Nation
- Construction start
- Dec 1, 2020(actual)
- Construction end
- Feb 25, 2022(actual)
Against the original forecast
- Construction start11 months lateforecast Jan 15, 2020
- Construction end13 months lateforecast Feb 1, 2021
Also in Cape Breton
- Cape Breton Regional Municipality - Wastewater Treatment Infrastructure$39.2M
- Cape Breton University - Centre for Discovery and Innovation$20.0M
- Eskasoni First Nation Long Term Care Kiknu$19.7M
- Sydney Harbour West Wastewater Collection and Treatment$19.3M
- CBRM - Battery Electric Bus Purchase and Storage and Maintenance Facility - Phase 2$16.7M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54342 in the federal list. How to read these figures.