Housing Nova Scotia Public Housing Building Envelope and Systems Deep Energy Retrofit
Federal contribution
$11.0M
$11,000,000
Federal share47%
of $23.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 3, 2019
2020202220242026
BuiltForecast
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Housing Nova Scotia
- Construction start
- Aug 6, 2019(actual)
- Construction end
- Jun 30, 2026(forecast)
Against the original forecast
- Construction start3 weeks lateforecast Jul 15, 2019