Route 114 to Fundy National Park - Surface Rehabilitation

Albert County, New Brunswick

completeHighways and RoadsRNIS
Federal contribution
$1.4M
$1,382,549
Federal share50%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 29, 2019
Built

Approved 3 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Aug 7, 2019(actual)
Construction end
Oct 24, 2019(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jul 22, 2019
  • Construction end8 weeks lateforecast Aug 30, 2019