Bus Bypass Shoulder (BBS) on Highways 13, 15, 25 and 640

Boisbriand, Quebec

completePublic TransitPTIS
Federal contribution
$850,639
Federal share40%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 19, 2020
2020
Built

Approved 9 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
Province of Quebec
Construction start
May 19, 2020(actual)
Construction end
Sep 28, 2020(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 4, 2020