Schedule
Announced and approvedAug 23, 2019
2020202120222023
Built
Approved 4 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Three Rivers
- Construction start
- Dec 2, 2019(actual)
- Construction end
- Mar 31, 2023(actual)