Birtle Transmission Line
Federal contribution
$12.0M
$12,027,017
Federal share50%
of $24.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 2, 2020
202020212022
Built
Approved 7 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Manitoba Hydro
- Construction start
- Nov 1, 2019(actual)
- Construction end
- Mar 31, 2022(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Dec 2, 2019
- Construction end4 months lateforecast Nov 30, 2021
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54399 in the federal list. How to read these figures.