Birtle Transmission Line

Ellice-Archie, Manitoba

completeGreen EnergyGIS
Federal contribution
$12.0M
$12,027,017
Federal share50%

of $24.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 2, 2020
202020212022
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Manitoba Hydro
Construction start
Nov 1, 2019(actual)
Construction end
Mar 31, 2022(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Dec 2, 2019
  • Construction end4 months lateforecast Nov 30, 2021

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54399 in the federal list. How to read these figures.