Conversion of heating systems in Inukjuak’s social housing installations: from oil to a dual-energy heating system (electricity/fuel oil)

Inukjuak, Quebec

completeGreen EnergyGIS
Federal contribution
$5.3M
$5,325,000
Federal share45%

of $11.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 5, 2025
202020212022202320242025
Built

Approved 5.5 years before the announcement.

Program
Green Infrastructure Stream
Construction start
Jul 9, 2020(actual)
Construction end
Jan 31, 2025(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 6, 2020
  • Construction end4 months lateforecast Sep 30, 2024

Also in Inukjuak

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54414 in the federal list. How to read these figures.