Wood Islands Lighthouse Infrastructure Improvements

Woods Island, Prince Edward Island

completeCultureCCRIS
Federal contribution
$28,010
Federal share38%

of $73.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 23, 2019
20202021
Built

Approved 4 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Sep 11, 2019(actual)
Construction end
Nov 3, 2021(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 15, 2019
  • Construction end2 months lateforecast Aug 28, 2021

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54430 in the federal list. How to read these figures.