Large Culvert Replacement - Gaspereau Creek No.1 (Route 116)
Federal contribution
$544,872
Federal share50%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 26, 2019
2020
Built
Approved 4 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- New Brunswick Department of Transportation and Infrastructure
- Construction start
- Jul 13, 2020(actual)
- Construction end
- Oct 16, 2020(actual)
Against the original forecast
- Construction start10 months earlyforecast May 17, 2021
- Construction end12 months earlyforecast Oct 29, 2021
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54437 in the federal list. How to read these figures.