Regular Bridge Replacement - Nash Creek No.1 (Route 134)

Nash Creek, New Brunswick

completeHighways and RoadsRNIS
Federal contribution
$1.1M
$1,150,000
Federal share50%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 29, 2019
2020202120222023
Built

Approved 3 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Sep 20, 2021(actual)
Construction end
Jul 7, 2023(actual)

Against the original forecast

  • Construction end7 months lateforecast Nov 30, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54438 in the federal list. How to read these figures.