Paving - Route 105 Keswick River No.1 to Route 616
Federal contribution
$869,685
Federal share50%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 10, 2021
20202021
Built
Approved 19 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- New Brunswick Department of Transportation and Infrastructure
- Construction start
- Aug 19, 2019(actual)
- Construction end
- Nov 9, 2019(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jul 29, 2019
- Construction end6 weeks lateforecast Sep 28, 2019
Also in Keswick