Paving - Route 105 Keswick River No.1 to Route 616

Keswick, New Brunswick

completeHighways and RoadsRNIS
Federal contribution
$869,685
Federal share50%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 10, 2021
20202021
Built

Approved 19 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Aug 19, 2019(actual)
Construction end
Nov 9, 2019(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jul 29, 2019
  • Construction end6 weeks lateforecast Sep 28, 2019

Also in Keswick

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54441 in the federal list. How to read these figures.